PARKADE UPDATE       October 14, 2011

 

Ø LEVELS 16-17-18 ARE EXPECTED TO BE COMPLETE BY THE END OF NOVEMBER.

 

Ø WE HAVE GIVEN PERMISSION FOR REDCO TO WORK ON SATURDAYS SO THEY CAN COMPLETE THE REPAIR BEFORE THE COLD WEATHER HITS.

 

Ø WE WILL BE REMOVING THE ASPHALT FROM LEVEL 13 & 14 THIS FALL SOMETIME AROUND MID OR LATE NOVEMBER. DATES STILL HAVE NOT BEEN CONFIRMED. 

 

Ø LEVELS 11 & 12 WILL NEED TO BE VACATED FOR DAYTIME HOURS (8AM - 5PM) DURING THIS PERIOD.

 

 

Ø PARKADE ACCESS WILL BE MOVED TO ALLOW REDCO TO COMPLETE THE SECOND HALF OF LEVEL 18.  SIGNS WILL BE POSTED AND ACCESS WILL BE WITH YOUR AMENITIES KEY.